Emergency Work — Kerja Kecemasan
Emergency Module overview · Phase 1Emergency work covers unplanned response to incidents that make a federal road unsafe or impassable — landslides, washouts, flooding, sinkholes, fallen trees, structural failure and crash damage. Unlike Berkala (programmed, budget-led) and Routine (cyclic, SLA-led), emergency work is event-driven: the clock starts at the report, not at the programme.
The module runs the full incident lifecycle — intake from the public and the district, triage into a response class, road-status control (closure, contraflow or diversion), dispatch to the zone contractor, and closure with photographic evidence for the claim. Work is made safe first and valued after, so every order carries a post-hoc certification trail rather than a pre-priced scope.
Response targets follow the incident's safety consequence, not its cost. E1 is measured in hours because the road is closed or life-safety is exposed.
Response Classes
Triage Target is time-to-make-safe, not to completeRoad impassable or life-safety exposed. Immediate make-safe, verbal approval, ratified after.
Serious hazard to traffic but the route stays open under control. Same-day attendance.
Damage that will worsen or become unsafe if left. Attended within the working week.
Stabilised incident held under watch, or handed to the Berkala / Routine stream.
Incident Categories
EM1–EM8 Scope of the emergency registerCut/fill slope collapse, rockfall, debris on carriageway, slope crack movement
Carriageway flooding, embankment washout, scour, drainage overwhelm
Sinkhole, subsidence, blow-up, sudden large-area pavement collapse
Bridge strike, bearing or parapet failure, culvert collapse, scour at abutment
Trees, branches, landslip debris and spilled load blocking the carriageway
Guardrail, barrier, sign, lamp post and furniture damaged by vehicle impact
Street lighting blackout, signal failure, exposed cabling, feeder pillar damage
Fuel, oil and chemical spill, surface contamination affecting skid resistance
Incident Lifecycle
Workflow Report → make-safe → claim- 1Report & intake T+0
Incident logged from the public, district, patrol or sensor. Location, photo and hazard captured.
Owner · Pusat Panggilan / MyJALAN - 2Triage & classification T+15 min
Verified and assigned a response class. Escalation triggers can force E1 regardless of category.
Owner · Pegawai Bertugas - 3Road status control T+30 min
Closure, contraflow or diversion declared and published. PDRM and district notified.
Owner · JKR Daerah - 4Dispatch & make-safe Within class target
Zone contractor mobilised to make the site safe — clear, sign, barrier, stabilise.
Owner · Kontraktor Zon - 5Permanent repair T+days
Full reinstatement, or handover to Berkala / Routine if the scope suits a programmed stream.
Owner · JKR Daerah - 6Closure & claim T+14 d
Photographic evidence, measured quantities and post-hoc certification for payment.
Owner · Pegawai Penguasa
Intake Channels
Sources- ◆ MyJALAN public report — Citizen report with photo and GPS
- ◆ JKR Daerah — District office and duty officer
- ◆ Patrol & drive-through — Routine patrol sighting on the network
- ◆ PDRM / Bomba — Referral from emergency services on scene
- ◆ Sensor & CCTV — ITS feed, flood gauge and slope instrumentation
Escalation Triggers
Override Any one trigger forces the class- ▲ Carriageway impassable in any direction → E1
- ▲ Injury or fatality involved → E1
- ▲ Structural integrity in doubt → E1
- ▲ Active slope or embankment movement → E1
- ▲ Hazard within the running lane → E2
- ▲ Night-time blackout on a lit section → E2
How Emergency Differs
Context Against the other maintenance streams| Dimension | Berkala | Routine | Emergency |
|---|---|---|---|
| Trigger | Condition survey | Cyclic schedule | Incident report |
| Clock starts | Budget year | Cycle date | Time of report |
| Target | Programme delivery | SLA in days | Make-safe in hours |
| Pricing | Tendered scope | Measured rates | Post-hoc certification |
| Approval | Pre-approved | Pre-approved | Verbal, ratified after |
| Road status | Lane management | Lane management | Closure / diversion |
Sample content for demonstration — response targets and category structure to be confirmed against JKR SOP Senggara Jalan before build.