Kerja Kecemasan
Triaj & Penugasan
August 2026 CURRENT CYCLE
Monthly cycle · response phase
Type
Zone
Response phase — from the report coming in to the action plan being set.
In Response
3
works not yet started on site
Awaiting JKR
2
assessment & action plan
TMP Late
0
past the 1-hour target
Average TMP
0.6 h
4 incidents attended
Awaiting TMP
Konsesi 1 incidentsTraffic Management Plan must be on site within 1 hour
Awaiting photos & notice
Konsesi 0 incidentsNothing waiting.
Photograph the original condition and notify JKR · JKR.PK(SJ).01.04.05-2
Awaiting JKR assessment
JKR 1 incidentsAssess the disaster type and decide the route to take
Awaiting action plan
JKR 1 incidentsLencongan or Pembersihan — fallen trees go straight to immediate action
TMP Performance
The flowchart requires the Traffic Management Plan to be in place on site within one hour of the incident being reported. It is the concession's first step, before photographs are taken and JKR is notified. 1-hour target from the report| ID | Type | TMP | Current stage |
|---|---|---|---|
| EMG-26011 | Chemical Spillage | 0.8 h | Photograph site & notify JKR |
| EMG-26034 | Banjir | 0.7 h | Photographic report & NOE |
| EMG-26005 | Structure Collapse | 0.5 h | Photographic report & NOE |
| EMG-26036 | Structure Collapse | 0.5 h | Set action plan |